Water System Improvement Project

The Warminster Municipal Authority has begun water main construction projects in several areas throughout the Township. The hours of operation will be between 7:00 a.m. and 5:00 p.m., weather permitting. On Monday, May 10, 2021, the contractor will be starting work on Valley Road between Carr Way and Street Road. 

Work on County Line Road at Woodland Avenue from east on County Line Road toward York Road is completed. Work on County Line Road from Delmont Avenue to Norristown Road has started. The pipe installation portion of the water main replacement project on Claire Road from Gibson Avenue to Woodland Avenue is now completed. Trench paving on Claire Road and County Line Road from Woodland Avenue to York Road is completed. Final overlay paving will follow.

Water main and water service installation work is being done on Ivyland Road from York Road to Mearns Road.  Work on Davisville Road from Lilac Lane to Street Road, the intersection of Davisville Road and Overlook Drive, and Valley Road from Carr Way to Street Road has not started. 

If you have any questions concerning the impending work on this project, please feel free to contact the Authority office at 215-675-3301, ext. 201.  Also, an inspector will be on site daily who will be pleased to answer any questions you may have.

 

 

 

Status Update (chronological): 

On Monday, May 10, 2021, the contractor will be starting work on Valley Road between Carr Way and Street Road.